购买
下载掌阅APP,畅读海量书库
立即打开
畅读海量书库
扫码下载掌阅APP

5.2 Ground surface control survey

5.2.1 The coordinate and the elevation reference points shall be determined according to status quo of the existing control network in the project site,the coordinate and elevation systems,the network layout method,and the network hierarchy and the accuracy.When a construction control network is set up,the horizontal and elevation control networks should be used together with the local control network.

5.2.2 The horizontal control network may be based on the methods such as the satellite positioning survey method or the traverse survey method.On the premise of meeting the accuracy requirements given in Table 5.2.3-1 and Table 5.2.3-2 in this code,the horizontal control network may also be based on other network layout methods.

5.2.3 The horizontal control network survey technology shall comply with the following requirements:

1 The technical requirements for horizontal control network survey based on satellite positioning are shown in Table 5.2.3-1.

Table 5.2.3-1 Technical requirements for horizontal control network survey based on satellite positioning

2 The technical requirements for traverse control network survey are shown in Table 5.2.3-2.

Table 5.2.3-2 Technical requirements for traverse control network survey

Note: n is the single-way number of observation stations.

5.2.4 The elevation control network may be laid out once for all using the leveling survey method,or it may be laid out using the triangular elevation survey method of the same accuracy.The technical requirements for the elevation control network(leveling)survey are shown in Table 5.2.4.

Table 5.2.4 Technical requirements for elevation control network(leveling)survey

Note: L is the length of the return survey section or annexed or loop line(km),and n is the number of survey stations in the single trip.

5.2.5 A unified construction control survey system shall be established for the storage cavern construction section.The horizontal control coordinate system shall meet the requirements that the projection length in the entire storage cavern survey area shall not be greater than 25mm/km,and each tunnel portal shall be provided with at least three horizontal control points and two elevation control points. 2TwBAiIS6B1vK/2oTU7Ra6tG5q/CPuK2H2qDc09E4AdkhIu2q0LfbM9cAprFMfXN

点击中间区域
呼出菜单
上一章
目录
下一章
×

打开