购买
下载掌阅APP,畅读海量书库
立即打开
畅读海量书库
扫码下载掌阅APP

4.2 Vertically installed three-phase reactors

Ⅰ General requirements

4.2.1 Vertically installed three-phase reactors shall include vertically installed three-phase cement reactors and vertically installed three-phase dry hollow core reactors.

4.2.2 Aseismatic appraisal for vertically installed three-phase reactors shall focus on the examination of the reactor models and installation methods.

4.2.3 Aseismatic calculations shall be made for the vertically installed three-phase cement reactors used in the areas where the aseismatic precautionary intensity is 7 degree and above and the vertically installed three-phase dry hollow core reactors used in the areas where the aseismatic precautionary intensity is 8 degree and above in accordance with Chapter 5 of this standard.

Ⅱ Aseismatic appraisal

4.2.4 The aseismatic appraisal for vertically installed three-phase reactors shall meet the following requirements:

1 Vertically installed three-phase reactors should be dry hollow core reactors.

2 Three-phase reactors should be horizontally installed.

Ⅲ Aseismatic measures

4.2.5 If the vertically installed three-phase reactors fail to meet the aseismatic appraisal requirements in this section,aseismatic measures shall be taken in accordance with the following provisions:

1 In the areas where the aseismatic precautionary intensity is 6 degree or 7 degree,the vertically installed three-phase cement reactors should be changed to dry hollow core reactors,and in the areas where the aseismatic precautionary intensity is in 8 degree or 9 degree,the vertically installed threephase cement reactors shall be changed to dry hollow core reactors.

2 Vertically installed three-phase reactors should be changed to horizontally installed reactors where site conditions permit.

4.2.6 For the vertically installed three-phase dry air-core reactors used in the areas where the aseismatic precautionary intensity is 8 degree and above and the vertically installed three-phase cement reactors,if their aseismatic calculation fail to meet the aseismatic appraisal requirements,seismic strengthening may be made in accordance with Appendix B of this standard.

4.2.7 For the supporting porcelain insulators of the vertically installed three-phase dry air-core reactors in the areas where the aseismatic precautionary intensity is 7 degree and below or for the supporting porcelain insulators of the horizontally installed three-phase cement reactors,if their aseismatic calculation fail to meet the aseismatic appraisal requirements,such supporting porcelain insulators shall be replaced with the insulators in higher strength. se+s5nmrt7mykUw8ev7te6IW5QjCKVktJTwrz/HMboYJ+uK7cWU98tttbJdOtslI

点击中间区域
呼出菜单
上一章
目录
下一章
×

打开